bowl back in place waiting for plumbing to be reconnected. >>>
drain before being removed and reworked. >>>
Second layer of Derbibase, this one in permastic over the top layer of dens deck. >>>
clearance under some equipment after all insulation is installed... >>>
curb with the Derbi base vapor barrier >>>
The same, and a close up of the water tie off.
>>>
more conditions of the inside hvac area install... >>>
conditions... >>>
Iso over the Derbibase in Permastic, then
another layer of dens deck over iso, in olybond >>>
see face to right.... tearing off with a sawzall, and see guys legs in the maze... >>>
more tear off >>>
dens deck to the metal deck, covered with a layer of Derbibase in Permastic. Note solid water tie off, these remained in place... >>>
conditions... >>>
the tear off begins...
>>>
conditions.... >>>