English
English
Español
Français

Sign Up for Our E-News!

Join over 18,000 other roofers who get the Week in Roofing for a recap of this week's best industry posts!

Sign Up
NRCA - National Roofing Week 2024_04_09_2024
USG - Sidebar - Fire
Wil-Mar - Sidebar - Free Pipe Collar 10/23
CRRC - Annual Meeting Registration 2024 = Sidebar Ad
CCS-OpenForBusiness-Sidebar
Geocel - Sidebar - 50th Anniversary - Feb 2024
RoofersCoffeeShop - Where The Industry Meets!
English
English
Español
Français

FRSA S.T.A.R. Award Profile: 2016 Sustainable Project Winner

FRSA-2016-STAR-Sustainable-winner
July 13, 2017 at 7:59 a.m.

Anderson Roofing, Inc., won first place in the S.T.A.R. Awards sustainable category for the Lockheed Martin Solar Carport in Oldsmar, FL.

The Florida Roofing and Sheet Metal Contractors Association (FRSA) S.T.A.R. Awards – the Spotlight Trophy for the Advancement of Roofing – highlight industry projects throughout Florida.

FRSA members submitted their roofing projects completed during the previous year, along with an application detailing the project, and in-progress and completion photos for placement in one of six categories.

Project submission required a description including tear-off (if applicable), preparation, design work, installation, problem solving and any other information that might be unique to the job, such as safety requirements or field fabrication.

Categories for submission included: Sustainable, Community Service, Steep Slope, Low Slope, Specialty Metal, and Unique.

A panel of three industry professionals was established to review the submitted projects. Judging criteria included, but was not limited to: aesthetics, size, completion time, special circumstances, unique project design, complexity of project, workmanship, teamwork, testimonials, and creative problem solving. The judges selected three projects in each of the six categories to receive either first, second or third place S.T.A.R. Awards.

Advanced Roofing Inc won first place for their Lockheed Martin Solar Carport project. Their team consisted of:

  • Contractor: Robert Kornahrens
  • Project Manager: Paul Burns
  • Superintendent and Foreman: Josh Gordon
  • Manufacturer/Consultant: Advanced Green Technologies
  • Manufacturer: Hanwha Solar Panels
  • Manufacturer: Sungrow Inverters
  • Project MVP: Paul Burns

Headquartered in Bethesda, Maryland, Lockheed Martin is a global security and aerospace company that employs approximately 112,000 people worldwide and is principally engaged in the research, design, development, manufacture, integration and sustainment of advanced technology systems, products, and services. They are the largest industrial employer in Florida with approximately 12,000 employees in the state. The company’s Mission Systems and Training facility in Oldsmar, Florida employs about 500 employees and 100 contractors providing engineering, software development and other services for the company’s programs.

Project Background In 2014, Lockheed Martin contracted Advanced Roofing and sister company Advanced Green Technologies to design and build a massive 2.25-megawatt solar carport at their Mission Systems and Training facility in Oldsmar, Fla. The project encompasses 7,260 solar modules mounted on a 151,400 square foot area that is 24’ in height, which provides clean energy to the facility and protected parking for 534 vehicles.

Advanced Roofing was awarded the solar carport construction and solar installation project over seven other national contractors after a rigorous bidding process managed by Lockheed Martin. What Advanced Roofing brought to the table was not only experience in large-scale solar power installations in Florida but also the ability to both design and build the project.

The Process Advanced Roofing was the turnkey engineering, procurement, and construction (EPC) contractor on the Lockheed Martin project. The project scope included the entire parking lot asphalt replacement, installation of a custom designed steel carport structure with concrete foundations equipped with a solar power racking system, and an under-canopy LED lighting system. Overall, between Advanced Roofing and Advanced Green Technologies, the team was able to self-perform most of the overall project installation because of its in-house resources in roofing, sheet metal, cranes, and renewable energy.

Overcoming Challenges Being located in Florida, the carport solar array provided some design challenges due to the hurricane force winds that can access 150 miles per hour or more. Taking these wind loads into careful consideration, the team was able to make the adjustments and include in the structural design. And because Factory Mutual insures Lockheed Martin the project had to meet strict guidelines for the high-speed wind zone. "Any time that Factory Mutual becomes involved, projects become heavily scrutinized," mentioned Clint Sockman, Advanced Roofing Vice President of Renewable Energy.

Also, because of limited parking spaces during the construction process, the project had to be carefully phased so that employees had somewhere to park safely and the facility could continue to operate without disruptions.

Hanwha SolarOne Company provided the high-efficiency, S-series solar modules for the project, with inverters provided by SunGrow, and Advanced Green Technologies providing the steel carport structure. Components supplied for the project were rated for the Florida environment, such as wind resistance and corrosion resistance from saltwater spray. Issues like this were also taken into account with the steel structure and coatings on the steel structure, given that it is a 25-year energy production asset

Florida for the interconnection it was a fairly easy process as based Advanced Roofing’s experience a good understanding of Florida's regulations governing the tie-in of renewable power installations into the existing grid.

Furthermore, bringing an added “green” dimension to the environmentally friendly construction project, the team was able to recycle the inch-deep soil that was removed from the entire parking lot to donate to the City of Oldsmar’s new BMX Supercross facility that is nearby.

Conclusion The solar carport project was completed on time, and on budget without safety issues or disrupting the Lockheed Martin’s daily operations. Furthermore, upon completion of the solar project in September 2015 it held the title as the largest private, non-utility owned solar array in Florida at 2.25 Megawatts. The solar carport system can deliver significant savings to the Lockheed Martin overtime, cutting its utility costs up to 65 percent for annual savings of about $300,000. That's a savings of $6.5 million over 25 years, and a greenhouse gas emissions savings of 35 percent from deflecting energy consumption from conventional fossil fuel sources. In addition to the energy saving and reduced environmental footprint, the carport is also providing some much-appreciated shade for employees.

To learn more about the S.T.A.R. Awards, visit http://www.floridaroof.com/star-awards/



Recommended For You


Comments

There are currently no comments here.

Leave a Reply

Commenting is only accessible to RCS users.

Have an account? Login to leave a comment!


Sign In
LP Building Solutions - Banner Ad - Remodlers Edge
English
English
Español
Français

Sign Up for Our E-News!

Join over 18,000 other roofers who get the Week in Roofing for a recap of this week's best industry posts!

Sign Up
SOPREMA - Sidebar Ad - The Right Coatings for the Right Roofs (RLW on-demand)
McCormack Succession and Exit Planning - Sidebar Register
ABC Supply - Sidebar Ad - Solar Distribution
Metal-Era / Hickman - Sidebar Ad - Product Launch
Polyglass - Sidebar - PolyAnchor - April 2024
GCMC-Podcast-WinTraining-Sidebar-2